Decouple

A Case Study of Excellence from Canada’s Nuclear Golden Age

Jan 29, 2026
Ken Petrunik, a veteran Canadian nuclear project leader who delivered CANDU reactors worldwide, shares stories from Romania, China, Argentina and more. He recounts how Qinshan Phase III finished early and under budget. The conversation covers construction sequencing, on-site problem solving, team selection, decision authority, and what was lost as Canada's build capability faded.
Ask episode
AI Snips
Chapters
Transcript
Episode notes
INSIGHT

Teamwork Built Canada’s Nuclear Lead

  • Canada succeeded in nuclear through a federal-provincial partnership combining AECL, Ontario Hydro/OPG, and domestic industry.
  • Recreating that coordinated ‘Team Canada’ approach is essential to relaunch Canadian reactor technology.
ADVICE

Align Owner, Vendor, And Contractors

  • Work as a single integrated entity with the owner and contractors to eliminate finger-pointing and speed delivery.
  • Use shared incentives and transparency to align priorities and recover schedule risk quickly.
ANECDOTE

Open-Top Reactor Saves The Schedule

  • Ken chose an open-top reactor strategy so heavy equipment could be installed from the side using a heavy-lift crane.
  • That early decision let the team install delayed steam generators without rework and protected the critical path.