Derek White from Ascot Resources discusses pouring first gold at Premier Gold Project in British Columbia. The team navigated challenges during construction, aiming for commercial production by Q3 2024. They focus on system fine-tuning and overcoming operational hurdles, highlighting the significance of this milestone.
Ascot Resources completed their first gold pour at the Premier Gold Project in British Columbia, marking a significant milestone in their operations.
Challenges during the mill commissioning phase, such as electrical issues and furnace alignment, required agile problem-solving skills to ensure operational success.
Deep dives
Ascot Resources Successfully Completes First Gold Pour at Premier Gold Project
Ascot Resources reached a significant milestone as they completed their first gold pour at the Premier Gold Project in British Columbia. CEO Derek White expressed gratitude for the effort involved in the project, highlighting the various stages from feasibility studies to commissioning. While the process is complex and involves ongoing monitoring and testing, the team anticipates further gold pours in the coming weeks to refine the product. The focus now shifts to the commissioning of the mill and increasing mining development to meet upcoming targets.
Challenges and Progress in Commissioning Process
The commissioning process at Ascot Resources involves meticulous testing and alignment of various systems to ensure optimal operations. Though challenges such as electrical issues and induction furnace commissioning occurred, the team's agility and problem-solving skills have been instrumental in overcoming hurdles. As the construction phase transitions to operational control, the focus is shifting towards fine-tuning processes and achieving a steady production state. The company looks forward to commercial production in Q3, aiming to capitalize on the current high gold prices for project profitability.
Derek White of Ascot Resources joins us to talk about the milestone achievement of pouring their first gold at the Premier Gold Project in British Columbia. The pour happened as part of the mill's commissioning phase. The construction phase is coming to an end, and the operations are starting, although there are still some hurdles to overcome. The company plans to continue pushing mining development and commissioning the mill in the coming months. The goal is to achieve commercial production in Q3 of 2024. The first gold pour is a significant milestone, and the team is working towards fine-tuning the systems and getting everything working smoothly.
Get the Snipd podcast app
Unlock the knowledge in podcasts with the podcast player of the future.
AI-powered podcast player
Listen to all your favourite podcasts with AI-powered features
Discover highlights
Listen to the best highlights from the podcasts you love and dive into the full episode
Save any moment
Hear something you like? Tap your headphones to save it with AI-generated key takeaways
Share & Export
Send highlights to Twitter, WhatsApp or export them to Notion, Readwise & more
AI-powered podcast player
Listen to all your favourite podcasts with AI-powered features
Discover highlights
Listen to the best highlights from the podcasts you love and dive into the full episode