The KE Report

Troilus Mining – A Gold-Copper Project Of Scale, Capital Stack Coming Together, Basic And Detailed Engineering Studies, Permitting Progress, And Exploration Upside

Dec 9, 2025
Justin Reid, President and CEO of Troilus Mining Corp., shares insights on the impressive Troilus gold-copper project in Quebec. He highlights a projected 22-year mine life and the strategic importance of copper in securing financing and offtake agreements. Reid discusses significant advancements in engineering studies and the recent increase in their debt financing mandate to $1 billion. With 13 million gold equivalent ounces already established, he emphasizes ongoing exploration efforts in the Southwest Zone and their plans to enhance the project's potential.
Ask episode
AI Snips
Chapters
Transcript
Episode notes
INSIGHT

Project Scale And Metal Mix

  • Troilus is a 22-year mine life project in central Quebec with 50,000 tpd throughput and ~75–80% gold, 20–25% copper revenue mix.
  • Copper materially boosts revenue and strategic financing interest alongside a gold-forward profile.
ADVICE

Use ECA Debt As A Financing Lever

  • Secure ECA-backed senior project debt as a cornerstone and use mandated lead arrangers to manage due diligence.
  • Upsize debt when commodity prices and DD improve to reduce other capital needs and accelerate financing certainty.
INSIGHT

From Basic To Detailed Engineering

  • Basic engineering is complete and the team is transitioning to detailed engineering and optimization of throughput and costs.
  • Execution planning focuses on sequencing, staffing and logistics to avoid capital overruns from poor planning.
Get the Snipd Podcast app to discover more snips from this episode