Ep.1174 - Advanced Pull Planning

6 snips
Sep 25, 2024
Delve into advanced pull planning techniques that uncover accurate task durations in construction. Discover strategies for identifying workflow bottlenecks and improving efficiency through better trade partner coordination. The discussion also covers integrating pull planning with methods like line of balance and tact, while emphasizing the need for accuracy to ensure successful project delivery. Tune in for insights that enhance collaboration and streamline construction processes!
Ask episode
AI Snips
Chapters
Transcript
Episode notes
ADVICE

Pull Planning Basics

  • Start pull planning by declaring conditions of satisfaction and clarifying milestones.
  • Explain the sequence and job site needs in a forward pass, then explain each trade partner's needs in a backward pass.
ANECDOTE

Five-Day Activity Pull Plan

  • Jason Schroeder observed a pull plan where every activity was five days long, likely due to trade partners anchoring to the previous duration.
  • The superintendent then shortened durations randomly without consulting the trades, counter to LeanTakt principles.
ADVICE

Advanced Pull Planning

  • Instead of asking for average durations, ask trade partners for their fastest, average, and slowest durations for each task.
  • Also ask for their smallest, average, and longest tack time stagger between activities.