Silver Tiger Metals – Ongoing Development Work On The Ground At The Stockwork Zone, Imminent Underground PEA, Regional Drill Program, and Capital Management

Jan 7, 2026
Glenn Jessome, President & CEO of Silver Tiger Metals, shares exciting advancements in the El Tigre silver-gold project in Mexico. With all necessary permits secured, he discusses the ongoing construction and engineering preparations for a robust 18-month plan. Glenn highlights an imminent underground Preliminary Economic Assessment (PEA), emphasizing high-grade silver-gold potential. He also outlines upcoming regional drill programs and Silver Tiger's capital strategy moving into 2026, showcasing the company's commitment to growth and development.
Ask episode
AI Snips
Chapters
Transcript
Episode notes
INSIGHT

Engineering Head Start Cuts Build Risk

  • Silver Tiger completed most final engineering before permit, leaving only minor items to finish after January.
  • This head start de-risks construction and accelerates the path to building the open-pit stockwork at El Tigre.
ANECDOTE

Share Gains Reflect Progress, Not Finish Line

  • Glenn recounts a rapid share-price run in 2025, up over 400% since the start of the year.
  • He frames that performance as early validation but stresses execution remains the critical next phase.
INSIGHT

Active Earthworks And Infrastructure Works Underway

  • Silver Tiger is executing multiple on-site works now: man camp earthworks, access road upgrades, and water-well drilling.
  • These actions prepare the site for year-round haulage and scale-up during construction and production.