Chris Elder, CEO of Fidra Energy and a veteran energy infrastructure executive, explores Britain’s race toward gigawatt-scale batteries. They discuss whether bigger really is better, how brownfield sites and grid access shape projects, making battery revenues bankable, the engineering challenge of building Thorpe Marsh, technology choices, gas’s reliability role, and looming market consolidation.
Ask episode
AI Snips
Chapters
Transcript
Episode notes
INSIGHT

Why Britain Needs Gigawatt Batteries

  • Britain’s 22–27 GW storage target cannot be met efficiently through scattered 50 MW installations alone.
  • Developers therefore need sites exceeding 500 MW to deliver capacity at the required pace.
ANECDOTE

Gas Sites Found A Second Life

  • Chris Elder repurposed gas sites after planned combined-cycle plants became uneconomic.
  • Existing consents and grid infrastructure enabled those sites to transition into large battery projects.
INSIGHT

Scale Makes Batteries Financeable

  • Large batteries combine lower unit costs with access to infrastructure-scale equity and project finance.
  • Chris Elder estimates 20–30% construction savings and 65–70% debt gearing for suitable projects.