013-Don't guess! Plan your project with SCIENCE using Monte Carlo analysis

Project Management Happy Hour

CHAPTER

How Does Monte Carlo Work?

The ranges on the input variables need to be based on data, as much as possible. The typical ranges that would be realistic are maybe minus 50% plus 200%. Some companies calibrate estimators by making them aware of their degree of conservatism.