The Pilot Face, the Pilot Face Is After?
I was the project manager for this sisisia project. That was between 19 93 and two thousandad six. The funding does not from the government, does not come from the tax payers. It comes from the waste producers. We have to adapt to the geoloe,. adapt the design to the geology. If you compare the tisue project and the swedish project, for instance, you can see differences. This is due to very different geological formations. All this was made during this period where i was project manager. And afterwards, had several er, e er, various positions in andre a programme management, safety, environment and now foresight and strategy