The History of Transmission

In the 70s, there was a big transmission build out. Then for years, we did nothing. Why? Is it because we had built out what we needed and there wasn't demand? Or was it actually bottlenecks? The next phase was sort of 2008 to 2013 where there was a pretty significant build out mainly wind energy driven MISO multi-value projects. And so, taking together, those led to roughly 4,000 miles of high voltage meaning like 345 KV and above Trent lines built in the year 2014.