The Cost of Interconnection to the Grid

"There's sort of no future where we don't have rising congestion costs overall in the absence of new transmission build out," he says. "Interconnection to the bulk power system used to take one or two years, now it's over four years on average." The cost has more than doubled as well: It used to be in the $100 a kilowatt range; now it's probably over 300.